Work is pushing on with the first paths in the Kippford Community Nature Reserve.

Recent rain has made working conditions a little more difficult, but Dempster’s are still making very good progress.

The tray (trench) for the 1.8m path has been fully excavated and the sub-base material should be finished in the next couple of days. There are then 6 culverts to be installed.

With two diggers working, excavation of the tray for the 1.2m tray will begin on Wednesday.

The work day is normally 7.30 - 4.00, so feel free to wander up after 4.00 pm and try out the 1.8m path!